ET410 Test

ALL MULTIPLE CHOICE

CHOOSE BEST ANSWER

 

 

QUESTION 1

 

The type of cost that generally increases in proportion to the degree they are in use is _______ costs.

 

 

direct

 

 

indirect

 

 

recurring

 

 

variable

 

 

QUESTION 2

 

Definitive cost estimates are accurate to the ______ %.

 

 

+/-30%

 

 

+/-50%

 

 

+/-5%

 

 

+/-10%

 

 

QUESTION 3

 

The last step in the risk management process is __________________.

 

 

risk mitigation strategies

 

 

risk and edification

 

 

an analysis of probability and consequences

 

 

control and documentation

 

 

QUESTION 4

 

____________ is the process of assigning the resource requirements for each project activity across the baseline schedule.

 

 

Resource leveling

 

 

Resource loading

 

 

Resource balancing

 

 

Resource efficiency

 

 

QUESTION 5

 

____________ offers a heuristic device for recognizing “peaks and valleys” in our commitment.

 

 

Resource leveling

 

 

Resource loading

 

 

Resource balancing

 

 

Resource efficiency

 

 

 

QUESTION 6

 

A _______________ chart illustrates the time-limited nature of resource scheduling.

 

 

resource leveling chart

 

 

resource loading chart

 

 

resource balancing chart

 

 

resource efficiency chart

 

 

 

QUESTION 7

 

_____________ variation is a cause that is inherent in the system .

 

 

termination cause

 

 

special cause

 

 

common cause

 

 

variable cause

 

 

 

QUESTION 8

 

______________ variation is a cause that is attributable to a special circumstance.

 

 

termination cause

 

 

special cause

 

 

common cause

 

 

variable cause

 

 

 

QUESTION 9

 

When applying the five steps in the theory of _____________, it is necessary to correctly identify the cause of bottlenecks or other areas of the activities of an organization.

 

 

risk

 

 

contingency

 

 

impact

 

 

constraints

 

 

 

QUESTION 10

 

What is the most important organizing tool project teams have to prepare their project tasks?

 

 

resource matrix

 

 

WBS

 

 

risk log

 

 

configuration management